Project Control

Project Control Services

ICARE can provide experienced personnel to support Project Managers in the areas of network scheduling, cost control, earned values, change control.

Project Initiation – the schedule will be based on milestone schedule and will create for the support of execution phase.

Progress Reporting – provide weekly/monthly reports, with the following content:

  • Progress status actual vs. planned
  • Progress “S” curve
  • Description of the work performed during previous period / Description of the work to be done during next period
  • Document control register
  • Project Schedule
  • Awaited information/hold points and Need List
  • Change Order status
  • Invoicing status

The planning documents are prepared by the Project Controls/Planning Engineer, based on information provided by the Leads of the Engineering/Design Disciplines.

Milestones Schedule

  • Time Schedule level I – Overall Project Schedule
  • Time Schedule level II – detailed by discipline
  • Time Schedule level III – detailed at package level

The Schedule is presenting the project milestones, all key activities with corresponding start/completion dates and durations, the critical path and float. The Project schedule is periodically updated with actual values and delivered with a Monthly Report.